Junction 42 Water Reservoir

Location

County of Red Deer, AB

Year Completed

2020

Location

County of Red Deer, AB

Year Completed

2020

Junction 42 Water Reservoir and Pump Station

Completed in Winter 2020

New construction of the Junction 42 Water Reservoir and Pumphouse facility and Distribution line, sitework and grading. Cast-in-place concrete reservoir tank (approx. 590 m3). Cast in place pumphouse foundations and precast tilt up concrete walls and hollowcore roof for Pumphouse. Interior and Exterior Architectural, Mechanical Plumbing / HVAC systems, Electrical Systems. Process Piping and distribution pump system consisting of 3 – 30 hp, 1- 50 hp electric drive water pumps, 1 – 75 hp Fire Pump. Outdoor Emergency Generator and Switch Gear. Electrical, Instrumentation system, VFD’s Chlorine Analyzers, MCC and controls.